Scope of Works
NWTD Stage 1 involves the upgrade and augmentation of the existing transmission network in North-West Tasmania and will support the connection of Marinus Link Stage 1 and the likely future demand from increased renewable energy production in Tasmania.
NWTD Stage 1 consists of the design, procurement and construction, pre-commissioning, and commissioning of; dual circuit 220kV Transmission Lines for Palmerston to Sheffield and Sheffield to Heybridge to Burnie (and the removal of the existing 220kV single circuit transmission lines between Palmerston to Sheffield and Sheffield to Burnie); substation augmentations at Palmerston, Sheffield and Burnie; and a new Switching Station at Heybridge to enable connection of Marinus Link into the Tasmanian 220kV transmission Network.
The initial Limited Notice to Proceed will incorporate the ECI Phase, to include engineering and design and surveys. Long lead time equipment and material procurement will follow under separate early works agreements during the LNTP phase. Following the ECI Phase, and subject to TasNetworks’ issuing a Notice to Proceed, the Construction Phase will then commence.
The Construction Phase of NWTD Stage 1 is subject to conditions including a Final Investment Decision, Planning and Environmental approvals, and the Australian Energy Regulator’s (AER) revenue determination, with the Construction Phase expected to commence Q2 2026 and scheduled for completion in 2029.