Pilbara Generation Project

Pilbara Generation Project
Location
Pilbara, WA
Client
Fortescue
Project dates
May 2023 - Present
Service
Infrastructure
Capabilities
Transmission & DistributionNetwork ServicesDesign & ConstructionSubstations
Pilbara Generation Project

Overview

Genus was awarded a circa $30 million contract with Fortescue for the completion of the key electrical works at the Pilbara Generation Project in North Star Junction, 26km west of Iron Bridge.

The works are underway with the GenusPlus workforce comprising approximately 80 personnel and is estimated to be completed in FY 2024.

Genus is also inviting equipment suppliers to provide an Expression of Interest for certain supply packages for the North Star Junction Solar Farm works. The Scope of Works is for supply only, and application information can be accessed via this link

 

 

Disciplines Employed

  • Supply
  • Installation
  • Modification works

Scope of Works

  • DC Reticulation
  • Install of Power Conversion Stations and access platforms
  • Installation of auxiliary equipment
  • Supply and installation of 33 kV overhead lines and Fibre Optic cables, and
  • Substation modification Works.

Outcome

The project is ongoing