Horizon Power 132kV Transmission Line

Horizon Power 132kV Transmission Line
Location
Karratha, WA
Client
Horizon Power
Project dates
December 2019 - November 2020
Service
Infrastructure
Capabilities
Transmission & DistributionTesting & CommissioningDesign & Construction
Horizon Power 132kV Transmission Line

Overview

The future energy needs of the Pilbara are being met with the Western Australian State Government investing more than $23 million through Horizon Power to upgrade the 132kV Transmission Line between Karratha and Dampier. The Transmission Line is a critical piece of electrical infrastructure in the Pilbara which connects the Karratha terminal substation to the Dampier substation.

Disciplines Employed

  • Design
  • Construction
  • Testing & Commissioning

Scope of Works

  • Two hundred old wooden poles were removed and replaced with steel poles in a new configuration which means the number of poles will be reduced by 65%, improving town aesthetics with the removal of more than 200 poles.
  • The work consisted of replacing approximately 15 kilometres of aged equipment on the existing 19km Transmission Line.
  • A section of the line near the Karratha Airport Terminal was undergrounded.

The phases of the works were as follows:

  • Design and Procurement Stage
  • Dismantling Old Line
  • Clearing, Surveying and Setting-Out Stage
  • Bulk Earthworks Pad Construction
  • Foundation Construction Stage
  • Pole Erection Stage
  • Transmission Underground Cable Installation
  • Stringing and Cut-In Stage
  • Commissioning and Handover Stage

Outcome

Commissioning on the 132kV Transmission Line took place in November 2020 bringing a successful end to the project.

The upgrade will reinforce the ageing infrastructure and ensure the security of supplies on the North West Interconnected System (NWIS) well into the future.

Image Gallery

Horizon Power